PHOTO GALLERY

  Reading is fine, but seeing is believing!!! Here's a glance of what we've been working at till now, and the way we did it.

You can find more pictures on Picasa.

Making blocks in the Auroville Earth Institute premises – November 2007


Precasting the caretaker’s house at the Auroville Earth Institute premises – December 2007



Building the caretaker’s house in 64 hours – February 2008

    Please visit the caretaker’s house for more information with a case study

Planting two trees named realization – 29th February 2008



Site preparation – March 2008



Block making on site – May 2008


Laying the foundation stone – January 2009



Rammed earth Foundation – January to April 2008



Plinth – May 2008



Ground Floor – June to July



Earth Tunnel – Rain water Harvesting – Julay to September 2009



Ring Beam – May 2009



Vaults and Domes – June to July 2009



Flooring Structure – August 2009



Roof Vault / Roofing – end of August to September 2009